Offshore wind Feed-In-Tariff requirements in Vietnam affecting UK exporters/investors
Trade barrier summary
To be eligible for the 20 year fixed Feed-In-Tariff (offshore $9.8c/kWh, onshore: $8.5c/kWh), wind developers need to have the Commercial Operation Date (COD) by 1 Nov 2021. The COD is the date after which all testing and commissioning has been completed and production for sale can begin. The deadline is too short for offshore wind projects licensed in 2020.
Sectors affected
- Energy
Resolved
No
Date reported
16 July 2020
Last updated
1 June 2022
Public ID
PID-MGXWPB
If a trade barrier is affecting your exports or investment from the UK, please let us know on report a trade barrier .